Configuration Guide for SMA Sunny Tripower Smart Energy Series: 5.0, 6.0, 8.0, 10.0

Written by Timo Streckfuß

Before you start

Before you begin, make sure:

  • The inverter is physically installed and powered on

  • The inverter is updated to the latest software version

  • The SMA 360° app is installed on your device

  • You are logged in to the SMA 360° app with your SMA ID


Step-by-Step Instructions

1. Connect the inverter to the network

  1. Connect an Ethernet cable to port D on the inverter

  2. Verify the connection is established by checking the blue LED on the inverter or in the SMA 360° app

image

For network infrastructure requirements and troubleshooting, see Infrastructure requirements for the gateway.

2. Access the inverter settings

  1. Open the SMA 360° app

  2. Select the inverter in the app and scan the QR code of the inverter

  3. Access the settings with the password that has been created during the initial setup

3. Enable communication via Modbus

  1. Navigate to
    Device configurationType of communication

  2. Configure the following Modbus settings:

    • Modbus active: Yes

    • Port: 502

    • Unit ID: 3

    • Modbus SunSpec profile version: Standard

  3. Save the settings

4. Discover the inverter in the commissioning wizard

The inverter is now ready for the commissioning wizard. The gateway will scan the network to find available devices, which may take a few minutes. Once complete, the SMA Sunny Tripower Smart Energy inverter will appear on the results page.

When the inverter is detected, in most cases set the asset type to Hybrid (PV and Battery) from the dropdown.

If you are using the inverter exclusively as a PV inverter, select PV System. If it is used solely as a battery inverter, choose Battery.


Country-specific configurations

Germany

Applies to PV installations exceeding 2 kWp installed after February 24, 2025.

For detailed information refer to §9 EEG (2025) – 60% feed-in limitation

No additional inverter configuration is required. The inverter controls the grid feed-in limit directly (GCP Limit), supporting energy management optimization.

Set the following Energy management setting in the commissioning wizard:

  • Allow optimisation: Yes

  • Grid feed-in limit controlled by inverter: Yes


FAQ

Why isn't the inverter appearing in the commissioning wizard?

Check that the inverter is connected via Ethernet at port D and that Modbus is enabled (Port 502, Unit ID 3). Restart the gateway and wait for the network scan to complete.

How do I update the firmware of the inverter?

Download the latest firmware from the SMA website and perform the update through the SMA 360° app.
For detailed update instructions, refer to the official SMA documentation.

What are the login credentials for the inverter settings?

The installer password is set during initial commissioning of the inverter. There is no factory default — you created the password the first time you accessed the inverter settings.

What if I have forgotten the installer password?

Perform a factory reset on the inverter to restore the original factory state. Refer to the manufacturer's documentation for reset instructions.


Supported models

  • Sunny Tripower Smart Energy 5.0

  • Sunny Tripower Smart Energy 6.0

  • Sunny Tripower Smart Energy 8.0

  • Sunny Tripower Smart Energy 10.0

Did this answer your question?