Before you start
Before you begin, make sure:
The inverter is physically installed and powered on
The inverter is updated to the latest software version
ViGuide is installed on your device and you are logged in with your certified Viessmann installer account
Step-by-Step Instructions
1. Connect the inverter to the network
Connect an Ethernet cable to the Ethernet port on the inverter
Verify the connection is established by checking the device display or in the ViGuide app
For network infrastructure requirements and troubleshooting, see Infrastructure requirements for the gateway.
2. Enable communication via EEBUS
EEBUS on the Viessmann Vitocharge VX3 cannot be configured via the inverter's control panel. Use the ViGuide app instead.
Open the ViGuide app and log in
Follow the instructions to complete the inverter setup in the App
Select External EMS and continue to the list of EEBUS devices
Select the gateway from the list of EEBUS devices
Complete the configuration to save the settings
3. Discover the inverter in the commissioning wizard
The inverter is now ready for the commissioning wizard. The gateway will scan the network to find available devices, which may take a few minutes. Once complete, the Viessmann Vitocharge VX3 inverter will appear on the results page.
When the inverter is detected, in most cases set the asset type to Hybrid (PV and Battery) from the dropdown.
If you are using the inverter exclusively as a PV inverter, select PV System. If it is used solely as a battery inverter, choose Battery.
4. Connect the inverter to the gateway
After the scan completes and the inverter is discovered, click Next in the commissioning wizard to proceed to the EEBUS connection screen.
On this screen, click Pair to initiate the EEBUS pairing process
Wait for coupling to finish and verify the connection
Country-specific configurations
Germany
Applies to PV installations exceeding 2 kWp installed after February 24, 2025.
For detailed information refer to §9 EEG (2025) – 60% feed-in limitation
No additional inverter configuration is required. The inverter controls the grid feed-in limit directly (GCP Limit), supporting energy management optimization.
Set the following Energy management setting in the commissioning wizard:
Allow optimisation:
YesGrid feed-in limit controlled by inverter:
Yes
FAQ
Why isn't the inverter appearing in the commissioning wizard?
Check that the inverter is connected via Ethernet and that EEBUS has been configured in the ViGuide app. Verify that the power limitation was set to Inactive during ViGuide setup. Restart the gateway and wait for the network scan to complete.
How do I update the firmware of the inverter?
You can perform the update through the ViGuide app.
For detailed update instructions, refer to the official Viessmann documentation.
Can I configure EEBUS via the inverter's control panel?
No. EEBUS configuration on Viessmann Vitocharge VX3 inverters is not available via the control panel. Use the ViGuide app to configure EEBUS and complete the pairing with the gateway.
Supported models
Vitocharge VX3