Before you start
Before you begin, make sure:
The inverter is physically installed and powered on
The inverter is updated to the latest software version
Step-by-Step Instructions
1. Connect the inverter to the network
Connect an Ethernet cable to the LAN1 port on the inverter
Verify the connection is established by checking the inverter display
For network infrastructure requirements and troubleshooting, see Infrastructure requirements for the gateway.
2. Access the inverter settings
Touch the sensor in the middle of the inverter to activate the access point
Scan the QR code on the inverter to connect
Log in as installer
3. Enable communication via Modbus
Navigate to
Communication → ModbusConfigure the following Modbus settings:
Modbus Server via TCP:
ActivatedModbus port:
502SunSpec Model Type:
int + SFMeter address:
240Allow control:
activatedRestrict control:
deactivated
Save the Modbus settings
4. Set control priorities
Navigate to:
Safety and network requirements → I/O power managementConfigure the following control priorities
Modbus controlas priority 1
Save the settings
5. Discover the inverter in the commissioning wizard
The inverter is now ready for the commissioning wizard. The gateway will scan the network to find available devices, which may take a few minutes. Once complete, the Fronius Symo GEN24 inverter will appear on the results page.
When the inverter is detected, in most cases set the asset type to Hybrid (PV and Battery) from the dropdown.
If you are using the inverter exclusively as a PV inverter, select PV System. If it is used solely as a battery inverter, choose Battery.
Country-specific configurations
Germany
Applies to PV installations exceeding 2 kWp installed after February 24, 2025.
For detailed information refer to §9 EEG (2025) – 60% feed-in limitation
The inverter controls the grid feed-in limit, supporting energy management optimization. The following inverter configuration is mandatory:
Navigate to
Safety and grid regulations → Export limitationConfigure the following Export Limit settings:
Power Control:
Total Power LimitExport Limit Control (Soft Limit): 60% of
Maximum grid feed-in powerinWExport Limit Protection (Hard Limit Trip): 60% of
Maximum grid feed-in powerinW
Save the settings
Set the following Energy management setting in the commissioning wizard:
Allow optimisation:
YesGrid feed-in limit controlled by inverter:
Yes
FAQ
Why isn't the inverter appearing in the commissioning wizard?
Check that the inverter is connected via Ethernet at LAN1 (not WiFi) and that Modbus is enabled with Modbus control set to priority 1. Restart the gateway and wait for the network scan to complete.
How do I update the firmware of the inverter?
You can perform the update through the Fronius Solar.web app or the web app. For detailed update instructions, refer to the official Fronius documentation.
What does "Forced Charging" mean on the inverter display?
This is normal when the gateway controls the battery. It's not an error.
Supported models
Symo GEN24
Symo GEN24 3.0
Symo GEN24 3.0 Plus
Symo GEN24 4.0
Symo GEN24 4.0 Plus
Symo GEN24 5.0
Symo GEN24 5.0 Plus
Symo GEN24 6.0
Symo GEN24 6.0 Plus
Symo GEN24 8.0
Symo GEN24 8.0 Plus
Symo GEN24 10.0
Symo GEN24 10.0 Plus
Symo GEN24 12.0 Plus SC
Symo GEN24 12.0 SC